{"id":120686,"date":"2023-11-02T17:19:36","date_gmt":"2023-11-02T17:19:36","guid":{"rendered":"https:\/\/yourclomid.com\/?p=120686"},"modified":"2023-11-02T17:19:36","modified_gmt":"2023-11-02T17:19:36","slug":"lukashenko-hits-out-at-putins-russia-after-nuclear-power-plant-issues","status":"publish","type":"post","link":"https:\/\/yourclomid.com\/world-news\/lukashenko-hits-out-at-putins-russia-after-nuclear-power-plant-issues\/","title":{"rendered":"Lukashenko hits out at Putin’s Russia after nuclear power plant issues"},"content":{"rendered":"

<\/p>\n

Cracks appear to have emerged in the relations between Belarusian President Alexander Lukashenko and his Russian counterpart Vladimir Putin, as the leader of the eastern European nation publicly called out Russia.<\/p>\n

The Belarusian leader said this week works have ended at the nuclear facility near the city of Astravets in the north-western region of Grodno.<\/p>\n

The nuclear power station, the only one in Belarus following the Chernobyl disaster in 1986, was built by Atomstroyexport, the nuclear equipment exporter branch of the Russian nuclear corporation Rosatom.<\/p>\n

In February 2009, Moscow agreed to an \u00a38.22billion ($10bn) loan for the construction of the plant, to be repaid by Belarus from 2021 over the next 25 years.<\/p>\n

The first energy unit was connected to the country\u2019s power grid in November 2020, but its operations were suspended several times for repairs.<\/p>\n

READ MORE: <\/strong> Zelensky blasted as closest aide claims Ukraine is ‘not winning’ war with Russia<\/strong><\/p>\n

<\/p>\n

The second unit was finalised in May, but the Ministry of Emergency Situations of Belarus issued a licence for its industrial operation several months later, on October 24.<\/p>\n

Attributing the delays experienced at the plant to Russia, Lukashenko said: “The commissioning timeframes of the nuclear power plant have slightly shifted because of the Russian side.<\/p>\n

“Naturally, under the contract, we raised the issue of compensation to them. There is no need to hide it.<\/p>\n

Don’t miss… <\/strong>
Russias pranksters catches Giorgia Meloni out as she admits Ukraine ‘fatigue'[INSIGHT] <\/strong>
Putin in trouble as ‘his control slips’ while he focuses on war in Ukraine[REPORT] <\/strong>
Nuclear disaster warning after ‘drones shot down near Ukraine power plant'[REPORT] <\/strong><\/p>\n

“There was nothing extraordinary there. But such questions were raised due to the fact that the deadlines for commissioning of the plant were violated, and the Russian side is responsible for it.<\/p>\n

“The Russian side offered compensation options in response. They also offered us options on the price of fresh nuclear fuel, as for Russians, as for their stations. And a warranty period of five years [for the main components].<\/p>\n

“We, of course, should not unnecessarily strain the Russians: we had enough electricity and still have enough, but an agreement is an agreement.”<\/p>\n